The Spring Creek Chapter of Trout
Unlimited (TU), the PA Fish and Boat Commission (PFBC), and ClearWater
Conservancy are currently partnering to complete the habitat restoration at the
former McCoy Dam site located between Bellefonte and Milesburg. August
restoration plans include construction of the floodplain bench, widening of the
stream channel, installation of 4 rock cross vanes, and several additional
instream habitat enhancement structures including 2 multi-log vane deflectors, 7
multi-log vane deflectors with root wads, 12 root wad deflectors, 4 modified mud
sills, and up to 30 Boulder Placements.
McCoy-Linn Dam was removed in 2007
through a partnership between PA Fish and Boat Commission, American Rivers, and
ClearWater Conservancy. The partnership removed the dam because it served no
functional purpose and created a public safety hazard, degraded water quality,
and impeded fish migration.
Construction Schedule
August 3 – Begin grading stream banks to establish new
floodplain bench and widen stream channel
August 10 – Begin rock cross vane installation
August 17 – Begin installation of instream habitat
enhancement structures
We anticipate all of the construction
to be completed by the end of August, weather permitting.
Future restoration plans include
riparian plantings in fall 2009 and public access enhancement including several
interpretive panels in spring 2009.
Restoration Updates - from
project manager Katie Ombalski
Plans
for Fall 2009
We will be planting the
riparian buffer this fall, so keep watching our website for new
updates.
Thank you to everyone for
your continued interest and support of this important project.
August
26, 2009
I stopped by the site early
this morning to see the work completed yesterday afternoon. Kenny from
Gleim had finished cleaning up the parking area and was heading out of
town to their next project in Pittsburgh.
On
behalf of Trout Unlimted, PA Fish and Boat Commission, and ClearWater
Conservancy, a sincere thank you to Gleim Environmental (I had to twist
their arm to take this photo) and WHM Consulting, Inc. (never could
corner Josh to pose) for a job well done!
Thanks
also to all of the volunteers and PA Fish and Boat Commission staff for
all of your hard work installing the habitat improvement structures!
Some before and after
photographs will be posted next week.
August
25, 2009
The
final rock cross vane was completed today.
Gleim
also worked with WHM to reshape the sediment from the former gravel bar
and to add a few small structures to the area just upstream from the
boat launch.
All instream work is now
complete!
August
24, 2009
The
third rock cross vane was completed today, and the remaining block stone
was delivered from the quarry for the fourth and final rock cross vane
that will be installed tomorrow.
Gleim
also installed the remaining root balls around some of the new habitat
structures.
The rye mix has started to
germinate thanks to the rain from last week, and the site is really
looking great.
Today
was a big volunteer day. About 10 Trout Unlimited volunteers are
working with PFBC staff and Gleim to install the remaining instream
habitat structures. They were able to install three log deflectors
before lunch and expect to install several more by the end of the day,
weather permitting.
The habitat structures will
be completed by noon tomorrow if all goes well. Gleim will then be able
to focus on completing the rock cross vanes.
Check out a YouTube video of
Gleim setting logs for a log deflector today.
Gleim
back filling a log deflector with stone.
Three completed log
deflectors.
Check out a YouTube video of
PFBC staff and TU volunteers completing the installation of a log
deflector.
Mark Nale visited the site
today to interview volunteers and staff about the project.
August
17, 2009
Progress today slowed but
Gleim was able to complete the second arm of the second rock cross
vane. Additional block stone was delivered for the remaining two rock
cross vanes.
August
14, 2009
The
first rock cross vane was complete today, and volunteers installed two
mudsills.
Gleim
was also able to incorporate three root wads into one of the arms of the
first rock cross vane. Installation was easier than expected with some
light excavation and by pushing against the root wad with the backhoe
bucket. The tree trunk slid right into the bank sediments.
Gleim
was also able to complete the first arm of the second cross vane before
leaving for the weekend.
August
13, 2009
The
site was seeded and mulched today. We are planning grain rye, riverbank
wild rye, and a PA ecotype of Virginia wild rye over the entire site.
We are also adding some wildflowers to a 30-foot strip along the road
that will be maintained as a permanent herbaceous buffer because of the
power line Right-of-Way. Spot seeding and mulching will continue
throughout the project as structures are completed.
Work continued on the first
rock cross vane.
Also check out a YouTube
video of today's seeding.
August
12, 2009
Logs
were delivered today so volunteers and PA Fish and Boat Commission staff
could begin building the first two log deflectors at the top of the
project site.
Once these structures were
completed, Gleim resumed work on the first rock cross vane.
The seeding contractor will
be on site tomorrow. Our goal is to have the entire site seeded by
Friday.
The following article was in
the Centre Daily Times today:
Also check out a YouTube
video of today's cross vane construction process.
August 11, 2009
Rock
deliveries and construction on the first rock cross vane started today.
Gleim
returned the wide-track bulldozer and exchanged it for an articulated
dump truck that will be used to transport the rock upstream. Normally
we would not transport construction materials via the stream channel but
the soft stream banks will not support the weight of the equipment.
The Centre Daily Times
was on site today.
August
10, 2009
We are seeing lots of
interesting wildlife on site including bald eagle, osprey, and mink.
Gleim
finished widening the stream channel and grading the floodplain bench
today. The last section of streambank is very wet. To prevent the
equipment from getting bogged down in the wet substrate, they place
large steel pads on the ground to increase the surface area for the
equipment to drive over. Gleim also used these pads during the initial
dam removal.
The gravel bar was also moved
today and all of this material was placed on the far streambank. The
purpose for doing this is to centralize the stream flow to keep the
pressure off of the stream banks.
PA
Fish and Boat posted “stream closed” buoys upstream of the project site.
The stream will remain closed until instream construction is completed.
We anticipate the stream re-opening at the beginning of September.
Construction materials will
start being delivered tomorrow.
August 6, 2009
Grading continues
August 5, 2009
Gleim rented a large-track bulldozer today. As a result,
the grading is much easier and the the equipment is not getting stuck like it
was yesterday. They completed approximately another 400 feet of grading today
and are now well over halfway done.
Josh Lincoln from WHM Consulting, Inc. and Dale Bentz from
Gleim have been visiting various rock piles and quarries to handpick rock that
will be used in the rock cross vanes. If all continues to go well, Gleim will
start building the cross vanes on Tuesday, Aug. 11.
Stream Bank Pre-Construction
Stream Bank Grading in Progress
Bank near the end of the day
August 4, 2009
The bulldozer got stuck several times today as result of
the clay pockets, so the grading progress was slower than Gleim had hoped
today. Even so, they were still able to complete approximately an additional
400 feet of grading today.
Morning
Afternoon
Before Construction
After Construction on August 4
August 3, 2009
2009
Stream Restoration Begins at the Former McCoy-Linn Dam Site.
Sunny weather provided great
working conditions. The contractor (Gleim Environmental) is starting at the
upstream end of the project and working downstream. Approximately 250 feet of
streambank and new floodplain bench was graded today.
Towards the end of the day, they
got to the stretch of stream that will be widened. As they started pulling back
the stream bank, they started getting into some pockets of clay that made
working conditions more challenging for the equipment.
August 1, 2009
Pre-construction looking downstream from the top of
the project site
Photos courtesy of Katie Ombalski.
For more information about the McCoy-Linn
Dam removal and restoration project, please contact project manager Katie Ombalski at (814) 237-0400 or
katie@clearwaterconservancy.org.